[LINK] NBN build cost 'underestimated': analysts
Bernard Robertson-Dunn
brd at iimetro.com.au
Fri Apr 8 14:29:57 AEST 2011
NBN build cost 'underestimated': analysts
Ben Grubb
April 8, 2011 - 12:39PM
SMH
http://www.smh.com.au/technology/technology-news/nbn-build-cost-underestimated-analysts-20110408-1d6xx.html
The $36 billion national broadband network is headed to a significant
cost blowout, analysts say, after the the company building it failed to
accurately predict the cost of construction when it took it to the market.
Last week the company building the network, NBN Co, wrote to 14
construction firms saying a key tender process was ''suspended''
indefinitely because none of their proposals had acceptable prices.
Following the suspension, NBN Co’s head of construction resigned,
fuelling speculation from Telsyte analyst Chris Coughlan that he was
"responsible for the assumptions in the business plan associated with
the construction costs". He made a "substantial mistake" and wasn’t
"able to land the deal".
Advertisement: Story continues below
And just today, The Australian reported that the company's manager of
cost and resource estimates, Nick Sotiriou, had also left the NBN Co.
"From time to time people have differences of opinion and that doesn't
mean one is right or wrong," he told The Australian. "And sometimes you
have to move on."
The newspaper also reported yesterday that companies it surveyed that
had put in a bid for the construction placed a 50 per cent premium on
the cost because NBN Co placed a lot of the build's risk on them.
The NBN Co would now be looking at ways to try and lower the cost of
construction, such as looking at the amount of overhead and underground
cabling, Telsyte's Coughlan said. Overhead cabling was sometimes
cheaper, he added.
NBN Co made the move to suspend the build tender because it believed the
bidders were trying to gouge excessive profits from the taxpayer-backed
project. But, according to some telecommunications analysts, rather than
price gouging occurring between bidders, the company may have
underestimated the build’s cost.
“I would find it very hard to believe and very legally difficult to
demonstrate collusion or a conspiracy has taken place,” said IBRS
analyst Guy Cranswick.
He said the ICT industry had been “very buoyant” about the NBN because
there was a “certain amount of self-interests that may [have] come into
play”.
“Now whether that motive has proved to show higher prices is very
difficult to prove,” he said. “There could be an underestimation on one
side but there could also be a certain enthusiasm about working for a
government backed corporation”.
Ovum telecommunications analyst, David Kennedy, said it was “clear” that
the tender process hadn’t “delivered a result consistent with the [NBN
Co] corporate plan”.
And despite the company’s claim it had been gouged, it was “difficult to
see” how that “could be sustained in a competitive process that’s been
going on for five months and in which there’s been ongoing negotiations
between NBN Co and the tenderers”.
Independent telecommunications analyst Kevin Morgan said the idea that
fourteen different companies “would all get together and all inflate
their prices” was “not realistic”. “It’s just not on.”
Morgan believed the build's cost had been underestimated and said that
it “wouldn’t be surprising” if the prices all came in at a roughly
comparable level “because the inputs are all pretty well known”.
“Where it may differ is in the element of risk that the contractor wants
to build into [their bid] because this is an extremely risky project
from the contractor’s point of view.”
Telecommunications analyst Paul Budde also questioned the gouging claim.
“If there was only one company or two companies involved with it” it may
be reasonable to suggest such a thing occurred, he said. “But there are
fourteen companies involved with [the tender]. They can’t all work in
that way. So I don’t think that that is a reality; that all of them in
one way or another have created a situation of gouging. I find it very,
very hard to believe. I mean, perhaps 20 years ago in the construction
industries things like that were happening but the construction industry
has become extremely professional in Australia and I can’t see that that
could happen on a massive scale”.
He said there might be “one or two” companies who would try to “use or
misuse” the tender process “but I don’t accept that the total
construction industry would do that”.
“So I think it, NBN Co, might refer to one or two situations where it
feels or expects that some of that has taken place but I don’t accept
that that would apply to the whole industry.”
The gouging ideology was also rejected by Telsyte's Coughlan. For price
gouging to occur, he believed that there would have had to of been
collusion. “And I very much doubt there’s collusion,” he said. “The
whole price gouging thing, I think, is a bit of a misnomer. I don’t
believe that [the bidders] are price gouging. I think some of the
respondents have probably done a fair bit of work in understanding the
costs and this is probably a big issue for NBN Co in that their business
plan assumes a certain [capital expenditure].”
Coughlan said one of the options NBN Co would be looking at now would be
partnering with Telstra on the construction of the NBN rollout further
than it already plans to. “However, at the end of the day, Telstra is
going to be using the same sub-contractors that all these construction
firms will be using. So the costs really aren’t going to substantially
change that much.”
Budde said Telstra was in a “unique position” to offer the services that
NBN Co was seeking in the tender but said that it “would be very
difficult” for NBN Co to give it to them because there “would be in
uproar” with people afraid that Telstra was becoming “so dominant in the
NBN business”.
Delays to the rollout as a result of the tender suspension were
inevitable, IBRS' Cranswick said.
“This will add more time and more delay and of course that will cost
money,” he said.
“I think all of these things add delay. They all compound, they all
knock on. And they all of course mean that corporations with a large
public quota have to consult with their executive boards and discuss how
they manage strategy, how they manage their dealings with such a large
corporation such as NBN Co. So yes, it causes delays all the way down
the chain; It produces a kind of negative feedback loop if you will.”
One analyst, who wished to remain anonymous, said that NBN Co may even
look to setup their own construction operation if they couldn’t get the
market to do the job at the price they wanted. “[The] easiest way to
kick that off would be to buy a construction company," they said. “[But]
that’s going to delay the project and they’ve said there’s not going to
be any delays."
The other option, the analyst said, was for NBN Co to "basically buy [a
construction company]" and build the network itself.
When NBN Co announced the indefinite suspension of the tender, a
spokeswoman for Communications Minister Stephen Conroy said it expected
the company to "negotiate the best rates on a building project, and
that's exactly what NBN Co are doing".
Opposition communications spokesman, Malcolm Turnbull, said the
suspension underlined the risk of cost blowouts, and cited industry
claims the government was underestimating the NBN's cost.
--
Regards
brd
Bernard Robertson-Dunn
Canberra Australia
email: brd at iimetro.com.au
website: www.drbrd.com
-----
No virus found in this message.
Checked by AVG - www.avg.com
Version: 10.0.1209 / Virus Database: 1500/3557 - Release Date: 04/07/11
More information about the Link
mailing list